Procurement Archives - C&I Engineering https://www.cieng.com/project_service/procurement/ C&I Engineering Tue, 01 Oct 2024 14:52:03 +0000 en-US hourly 1 Stillage Screens and Modular Boiler Installation https://www.cieng.com/projects/stillage-screens-and-modular-boiler-installation/ Tue, 01 Oct 2024 14:51:20 +0000 https://www.cieng.com/?post_type=project&p=3710  C&I performed a front-end study and detail design for this project.  The project required installation of a new water treatment...

The post Stillage Screens and Modular Boiler Installation appeared first on C&I Engineering.

]]>
 C&I performed a front-end study and detail design for this project.  The project required installation of a new water treatment and new boiler building in an operational distillery. Integration of systems must occur during a planned summer distillery outage and coincide with a major plant expansion. 

The stillage from the stills is separated in new screeners and the thick stillage is pumped a considerable distance across a road and railroad track to an Anerobic Digestion facility, designed by others. After processing, the C&I team piped the RNG back to the distillery and blended it with an existing natural gas feed to power the new modular boilers. The team has navigated the challenges of working with multiple vendors, permitting entities, and engineering firms to coordinate the design and installation of this project.

The post Stillage Screens and Modular Boiler Installation appeared first on C&I Engineering.

]]>
Tank Replacement Program https://www.cieng.com/projects/tank-replacement-program/ Fri, 28 Jan 2022 19:09:37 +0000 https://www.cieng.com/?post_type=project&p=1361 The goal of this project is to repair and/or replace aging tank assets. The client reached out to C&I due...

The post Tank Replacement Program appeared first on C&I Engineering.

]]>
The goal of this project is to repair and/or replace aging tank assets. The client reached out to C&I due to our expertise and familiarity with the parent company’s specifications and preferences. As an on-going program, we are able to help manage program budget, cash flow, and schedule. Our collaborative nature enables us to coordinate effectively with subcontractors and vendors. Our strong Civil & Structural department is overcoming design challenges of setting extremely large tanks in tight spaces. For example, we installed a new tank, 100,000 barrels, that was nearly double the capacity of the existing tank while keeping and repairing the existing tank for added capacity. We are excited to see this program progress while building a relationship with a new client.

The post Tank Replacement Program appeared first on C&I Engineering.

]]>
Urea Capacity Expansion https://www.cieng.com/projects/potash-urea-expansion/ Fri, 28 Jan 2022 19:07:38 +0000 https://www.cieng.com/?post_type=project&p=1409 This client sought to increase its urea capacity from 1,300 TPD to approximately 1,650 TPD to meet increasing market demand....

The post Urea Capacity Expansion appeared first on C&I Engineering.

]]>
This client sought to increase its urea capacity from 1,300 TPD to approximately 1,650 TPD to meet increasing market demand. This is due primarily to its ability to reduce NOX emissions in diesel engines while achieving a 4% to 7% increase in gas mileage. Because of the economic opportunities realized by increasing production capacity, C&I conducted FEL-1 conceptual phase through Detailed Design, Start-up and Commissioning.

To accurately model the process changes, our team created a benchmark simulation of the entire Urea Unit. Creating a Hysys model was a challenge and had to be rigorously tested. Due to the unique chemistry of the process, the urea and ammonium carbamate components had to be created and regressed binary interaction parameters for multicomponent mixtures had to be developed. Our model was validated against a test run, providing confidence in the simulation of future operation. The process team used creativity to address the need for supplemental compressed CO2 gas feed by using liquid CO2 to support the overall capacity increase.

The existing unit was congested, requiring finesse in siting equipment and routing piping. This is where our expertise in retrofit design combined with the 3D modeling tool and laser scan set us up for a successful project. We were able to involve stakeholders in a constructability review early in the design process to locate several new pieces of equipment in an existing structure.

The post Urea Capacity Expansion appeared first on C&I Engineering.

]]>
69 kV Substation Replacement https://www.cieng.com/projects/69-kv-substation-replacement/ Fri, 28 Jan 2022 17:23:27 +0000 https://www.cieng.com/?post_type=project&p=1389 The goal of this project was to replace antiquated electrical equipment, much of which was over 40 years old. Our...

The post 69 kV Substation Replacement appeared first on C&I Engineering.

]]>
The goal of this project was to replace antiquated electrical equipment, much of which was over 40 years old. Our team developed the scope from the Feasibility phase through Implementation, Start-up and Commissioning of the relay building and substation. C&I’s team drew on expertise from previous projects to assist with substation design, cutover planning and load balancing. We were able to work with the client to adjust project cash flow to coordinate with the turnaround schedule.

Due to geographical constraints, the project combined three substations into one. This resulted in multiple cutovers spread over 5 years to match turnaround outages. To make space for the new substation, several storage areas had to be relocated. After installation, the project finished $3MM under budget with minimal RFIs from construction.

The post 69 kV Substation Replacement appeared first on C&I Engineering.

]]>
ASO System Revamp for HF Alky Unit https://www.cieng.com/projects/aso-system-revamp-for-hf-alky-unit/ Fri, 28 Jan 2022 14:58:11 +0000 https://www.cieng.com/?post_type=project&p=1371 Leveraging our previous experience with Acid Soluble Oil (ASO) Washer Systems, our team provided insight on how systems are configured...

The post ASO System Revamp for HF Alky Unit appeared first on C&I Engineering.

]]>
Leveraging our previous experience with Acid Soluble Oil (ASO) Washer Systems, our team provided insight on how systems are configured at similar sites to thoughtfully execute the Feasibility phase of the project. At this facility, the current ASO neutralization and spent KOH handling system in the Hydrofluoric Alkylation (HF Alky) unit is a labor-intensive batch process that has many environmental and safety concerns. The system will be replaced with one that is similar to a ConocoPhillips (now UOP) ASO Washer system used at multiple other refineries. This will reduce the likelihood of environmental releases of HF acid and operator exposure to caustic, ASO and HF acid that are present during the manual process. As an added benefit, the new system will also result in operating cost savings.

The project will design and commission equipment which allows for continuous, closed loop treatment of ASO within the HF Alky unit.  As a cost savings, existing equipment will be repurposed where safety or integrity is not compromised. Drawing upon our experience from other refineries, our process team scaled the technology to match refinery flow rates based on comparison of ASO to Caustic ratios from other existing units. Our support on this project extended beyond creating a cost estimate, we also attended our client’s presentation to management. We not only care about project design, but the entire project process and are here to help our clients in any way we can!

The post ASO System Revamp for HF Alky Unit appeared first on C&I Engineering.

]]>
Primary 13.8kV Feeder to Unit https://www.cieng.com/projects/primary-13-8kv-feeder-to-unit/ Thu, 27 Jan 2022 21:51:30 +0000 https://www.cieng.com/?post_type=project&p=1374 Our team provided engineering design to install 13.8kV feeders as primary supply to the a major refinery unit via load...

The post Primary 13.8kV Feeder to Unit appeared first on C&I Engineering.

]]>
Our team provided engineering design to install 13.8kV feeders as primary supply to the a major refinery unit via load break switches to the unit’s substation transformers. This unit is integral to refinery profitability; therefore, increasing reliability to avoid an unexpected outage was a critical project objective. Reliability was improved by serving the unit’s load from independent 13.8kV feeders and extending the main-tie-main philosophy at each of the downstream distribution voltage levels present in the unit (4.16kV, 2.4kV and 480V), requiring addition of new equipment in the existing electrical building. Cable tray infrastructure was installed to support the new feeders.

The team was challenged to integrate new gear into the already congested operating unit. Our open communication and interactive project management style allowed us to involve maintenance, operations, and construction to balance project objectives and meet stakeholder needs.

The post Primary 13.8kV Feeder to Unit appeared first on C&I Engineering.

]]>
13.8 kV Substation Replacement https://www.cieng.com/projects/ird-southwest-substation/ Thu, 27 Jan 2022 21:25:51 +0000 https://www.cieng.com/?post_type=project&p=1383 Our team has been on the ground floor of the Electrical Upgrades program for this client; helping manage cash flow,...

The post 13.8 kV Substation Replacement appeared first on C&I Engineering.

]]>
Our team has been on the ground floor of the Electrical Upgrades program for this client; helping manage cash flow, identifying scope, and assisting with budget development. For this project, we completed Feasibility through Implementation to improve the plant reliability, flexibility and safety by replacing the existing substation electrical equipment with new upgraded components. By replacing the switchgear with an enhanced design, utilizing arc-resistant switchgear, and solid-state relaying schemes, the system is much safer and more reliable. The existing Sync Bus was replaced with a Ring Bus to improve reliability.

The criticality of this electrical gear required extensive planning to ensure the deenergizing and energizing did not result in any loss in production or safety incidents. Our team designed the equipment layout and purchased a new building to house the gear. We coordinated construction, operations, and maintenance to develop a staging plan for demolition and install.

Scope to accomplish this included larger capacity transformers, 13.8kV arc resistant switchgear with additional feeder capacity, new current limiting reactors and interconnecting cable bus. 

The post 13.8 kV Substation Replacement appeared first on C&I Engineering.

]]>
Flexible Hydrotreater https://www.cieng.com/projects/flexible-hydrotreater/ Mon, 24 Jan 2022 18:12:02 +0000 https://www.cieng.com/?post_type=project&p=1350 C&I initiated this project at Feasibility and saw it through to Detailed Design. The goal of this project was to...

The post Flexible Hydrotreater appeared first on C&I Engineering.

]]>
C&I initiated this project at Feasibility and saw it through to Detailed Design. The goal of this project was to gain ability to process naphtha and gas oil simultaneously, allowing the refinery to become flexible to market changes. In order to save our client significant capital investment and improve their ROI, our team took an outside-of-the-box approach of utilizing the reaction section and repurposing equipment. This strengthened our partnership and demonstrated our commitment to finding cost-saving opportunities for our clients.

A key component of this project was repurposing dated, idled equipment, requiring C&I involvement in fit-for-service evaluations. As part of this effort, we modified the charge heater to change the burners and add a burner management system that wasn’t there before. This required installation of a SIS infrastructure, which was used to support temperature monitoring on reactor and burner management system.

The post Flexible Hydrotreater appeared first on C&I Engineering.

]]>
Flare Gas Recovery Compressor https://www.cieng.com/projects/mpc-ird-flare-gas-recovery/ Mon, 24 Jan 2022 17:01:00 +0000 https://www.cieng.com/?post_type=project&p=1337 Our team worked with the client to address their flare gas consent decree, targeting high concentration H2S streams. Two approaches...

The post Flare Gas Recovery Compressor appeared first on C&I Engineering.

]]>
Our team worked with the client to address their flare gas consent decree, targeting high concentration H2S streams. Two approaches were taken. For one flare system, a new liquid ring compressor was installed. For the second flare system, we evaluated alternate technologies for reducing H2S through upgrades in the amine and sour water systems as an interim measure to meet the decree, ultimately lowering overall project cost.

There were three streams that the system could not recover, therefore C&I identified a method for recycling them back to the plant. By recycling these streams, we were able to save $3MM in total installed costs. We were one of the first to install this new compressor and worked directly with the vendor (SIHI) to ensure smooth engineering and install and to provide a reliable system for emissions reduction.

The site selected for the compressor required significant prep work, including filling in a pond and reworking drainage to other sewer systems. Our team routed over a mile of large bore piping, including a new pipe bridge, to tie the systems together.

The post Flare Gas Recovery Compressor appeared first on C&I Engineering.

]]>
Main-Tie-Main Switchgear Configuration https://www.cieng.com/projects/ird-crude-unit-main-tie-main/ Mon, 03 Jan 2022 21:09:48 +0000 https://www.cieng.com/?post_type=project&p=1378 C&I completed the Feasibility, Definition, and Implementation phases of this infrastructure upgrade project in order to improve the electrical reliability...

The post Main-Tie-Main Switchgear Configuration appeared first on C&I Engineering.

]]>
C&I completed the Feasibility, Definition, and Implementation phases of this infrastructure upgrade project in order to improve the electrical reliability for the Crude unit. To accomplish this, the existing single–source design with one (1) 13.8kV feeder and one (1) transformer at each voltage level was converted to a dual feed system with two (2) 13.8kV feeders, two (2) transformers, and a Main-Tie-Main (MTM) switchgear configuration at all voltage levels. To provide feed diversity, a second 13.8kV feeder from a separate substation was installed.  Additional reliability was achieved by extending the Main-Tie-Main philosophy to each of the downstream distribution voltage levels (4.16kV, 2.4kV, and 480V), which required dual transformation and double ended switchgear at each voltage level. 

To support the new electrical gear, a Power Distribution Center (PDC) was installed to house the 13.8kV and 4.16kv gear.  The existing brick substation was substantially modified internally to house the new 2.4kV and 480V gears.  In order to make this happen, the gear in the existing substation was removed and new gear was installed and tested on-site during a tight shutdown window, putting it on the critical path of the turnaround. Since there were other major upgrades occurring in the unit at the same time, C&I took the lead on a weekly coordination meeting with another engineering firm.

In addition to improved reliability, personnel safety was enhanced by providing arc resistant switchgear in a new PDC and electronic relay protective systems, providing high speed detection and clearing of electrical faults on the 13.8kV lines, transformers and switchgear buses at all voltage levels.  For added redundancy, the pump loads were redistributed so that A/B paired pump loads are split to separate switchracks fed from separate sides of the 480V MTM switchgear.  Three (3) new switchracks and a MTM configured MCC was included for the pump load redistribution and future 480V load expansion.  The 480V feeds to the switchracks were placed in a new cable tray system extending from the existing substation. 

The post Main-Tie-Main Switchgear Configuration appeared first on C&I Engineering.

]]>